Design and build: feasibility studies
Contents |
[edit] Introduction
The feasibility studies stage considers the options for satisfying the client's needs, enabling the client to prepare a business case for the preferred option and deciding whether to proceed with the project. It is possible to make an outline planning application during this stage if the risk to the project of not receiving planning permission is high, or if delays in receiving planning permission would be problematic.
[edit] Appointing a consultant team.
The client updates the preliminary business case and strategic brief to reflect comments made at the end of the previous stage and collates pre-construction information ready to issue to the consultant team.
The client appoints the consultant team and other advisers (including independent client advisers). For a detailed description, see work stage: Design and build: appointment.
The client chairs a consultant team start-up meeting to issue information to the consultant team. This is also an opportunity to establish collaborative practices and agree a programme.
The principal designer (if appointed) checks that the client is aware of their duties under the CDM regulations.
[edit] Developing the strategic brief.
The consultant team works with the client to help them develop the strategic brief sufficiently for feasibility studies and options appraisals to be carried out.
The consultant team assesses any site information issued to it by the client, and undertakes site appraisals. The consultant team obtains any further information about the site that might be required to undertake feasibility studies, such as site surveys, information about site services, site access conditions, legislative constraints, existing planning consents etc. Where necessary, approval should be sought from the client (for example site surveys requiring additional expenditure).
The lead consultant co-ordinates the preparation of feasibility studies to establish whether the project is viable, and to identify feasible options. The client considers the feasibility studies, and agrees which options the consultant team should develop.
[edit] Preparing an options review report
The lead designer co-ordinates the identification of any further site surveys or site information required to carry out options appraisals and where appropriate seeks approval from the client.
The lead consultant co-ordinates the preparation of a draft options review report:
- The lead designer co-ordinates the preparation of diagrammatic options studies;
- The principal designer (if appointed at this stage) assesses the risks of the options in relation to the CDM regulations;
- The architect co-ordinates consultations with the local authority and other statutory authorities, and assesses possible planning permission requirements and other statutory requirements (such as the need for an environmental impact assessment for the options). NB See the work stage: Design and build: planning permission for additional information;
- The cost consultant prepares initial cost appraisals of the options.
The client considers the draft options review report and either selects a preferred option or instructs the lead consultant to revise the options review report.
[edit] Preparing a business case and project execution plan.
The lead consultant co-ordinates further assessment of the preferred option to assist the client in preparing a business case and project execution plan, including:
- The lead designer establishes requirements for statutory approvals and other regulations with which the preferred option must comply;
- The lead designer co-ordinates consultations with utility providers, and
- The lead consultant co-ordinates an assessment of the need for specialist advice to develop the preferred option.
With the benefit of assessments carried out by the consultant team, the client develops the preliminary business case into a full business case and project execution plan for the preferred option.
The client considers, and if satisfied, approves the business case and project execution plan for the preferred option and gives instructions to proceed to the next stage, along with any other instructions that may be necessary.
At this stage, the client, lead designer and architect may consider whether it would be appropriate to make an outline planning application for the proposed development and direct the consultant team accordingly (if an outline planning application is required at this stage, go to the work stage: Design and build: planning permission).
Featured articles and news
Ensuring the trustworthiness of AI systems
A key growth area, including impacts for construction.
Foundations for the Future: A new model for social housing
To create a social housing pipeline, that reduces the need for continuous government funding.
Mutual Investment Models or MIMs
PPP or PFI, enhanced for public interest by the Welsh Government.
Stress Awareness Week ends but employer legal duties continue.
A call to follow the five Rs for the business and for the staff.
Key points and relevance to construction of meeting, due to reconvene.
Cladding remediation programmes, transparency and target date.
National Audit Office issue report on cladding remediation.
HBPT and BEAMS Jubilees. Book review.
Does the first Labour budget deliver for the built environment?
What does the UK Budget mean for electrical contractors?
Mixed response as business pays, are there silver linings?
A brownfield housing boost for Liverpool
A 56 million investment from Homes England now approved.
Fostering a future-ready workforce through collaboration
Collaborative Futures: Competence, Capability and Capacity, published and available for download.
Considerate Constructors Scheme acquires Building A Safer Future
Acquisition defines a new era for safety in construction.
AT Awards evening 2024; the winners and finalists
Recognising professionals with outstanding achievements.
Reactions to the Autumn Budget announcement
And key elements of the quoted budget to rebuild Britain.
Chancellor of the Exchequer delivers Budget
Repairing, fixing, rebuilding, protecting and strengthening.
Connecting conservation research and practice with IHBC
State of the art heritage research & practice and guidance.